Completed and Past Projects

COMPLETED PROJECTS 2018:

 Center Blvd Pier Reinforcement Project 01/03/2018 - 01/12/2018

COMPLETED PROJECTS 2017:

2017 Hub Study

 Pine St and San Anselmo Ave Bench Tree Uplift Repair
Repair concrete uplift from tree roots.

Brookside Sidewalk Gap Project

 RVSD Pipe Lining 12/7/17 through 12/8/17
 Pipe lining work on Humboldt 12/7/17 and 12/8/17. The lining work does not damage the pavement. The contractor and project manager have asserted that there will be a maximum 5 minute delay for traffic on Humboldt between Forrest Ave and Foothill Ave.  

 Crack Seal Project on 11/13/17 (rescheduled for December 1, 2017)
Map of the Dec 1 Crack Sealing
 The Town has contracted Graham Contractors Inc (GCI) to perform crack sealing on various streets in San Anselmo. Crack sealing can help extend the life of a roadway, reduce pavement failures, and slow down deterioration. This form of preventative maintenance saves money by delaying major reconstructive pavement work.   

Impacts to residents and motorists are minimal with crack seal maintenance, which is generally a fast- moving process. Streets are not closed during the work, however drivers may be asked to wait a few (less than 5) minutes for a sealant to cure before being allowed to drive over it. This helps keep vehicles free of the sealant material and allows the material applied to the roadway to create a stronger longer-lasting seal.

 Some noise is associated with the initial step to prepare the cracks when a high pressure compressor is used; however this is usually only for short periods of time. The duration of noise is dependent on how many cracks are in need of maintenance on a given roadway. 

PG&E work on Sais 2017

Sir Francis Drake Blvd Night Paving on May 15, 2017 Letter to Owners/Residents

PG&E Gas Main Upgrade on Sais Avenue 02/2017

Lansdale Avenue Traffic Calming Project Construction Postponed 
 The asphalt stamping and painting of five intersections on Lansdale Avenue in Fairfax and San Anselmo scheduled for November 7-11 has been postponed until warmer temperatures next Spring. We apologize for the delay, and will schedule the work as soon as the weather is conducive.

Gravel Sweeping
There will be no parking signs going up around town for a system wide gravel sweep. Since our slurried streets are rarely empty enough to properly sweep the parking lanes, we have decided that temporary no parking zones must be established to get a good clean sweep. 

 The streets and associated dates are shown on the map below:
Temporary No-parking Zones for Gravel Sweeping: Map

San Francisco Blvd and Veterans Place Gas line Replacement 

2016 Sir Francis Drake Blvd Paving Project Phase 2


Project Number 2016SR

Notice to Bidders 
Bids were opened July 5, 2016. The selected bidder is Ghilotti Bros. Inc.
Bid Abstract

Notice to Bidders
The Town of San Anselmo is inviting sealed proposals for the 2016 Pavement Rehabilitation and Preservation Project (Sir Francis Drake Blvd Paving Project Phase 2).
Addendum #1
Notice to Bidders
Plans
Specs
Bid Book (Not for Submittal)

Lansdale Avenue Traffic Calming Project Construction 
The asphalt stamping and painting of five intersections on Lansdale Avenue in Fairfax and San Anselmo has been completed.

Bolinas Avenue/Sir Francis Drake Improvement Project
The Towns of Ross and San Anselmo are pleased to announce an upcoming federally-funded project to widen the sidewalk on Bolinas Avenue between Shady Lane and Sir Francis Drake Boulevard, and to enhance the bus stops on Sir Francis Drake Boulevard at Bolinas Avenue.

The project consists of installing 10 new curb ramps, widening sidewalks, traffic signal improvements, and paving Sir Francis Drake Boulevard from 225 feet south of Winship Avenue to 230 feet north of the Bolinas Avenue intersection, as well as the Bolinas Avenue/San Anselmo Avenue intersection.

The concrete work will take about four weeks starting September 6. The work will take place during normal work hours (8 am to 5 pm weekdays), with work that requires traffic control limited to 9 am to 3 pm. The final paving work is tentatively scheduled for the week of October 3. The exact dates and times of paving work will be advertised a couple of weeks in advance.

The contractor will provide a pedestrian path-of-travel through the work site during construction. The bus stops will be temporarily relocated a short distance way. Marin Transit will post information about the relocated stops in advance of the work.

The Towns would like to thank you for your patience while we undertake this important project.

If you have any questions, please contact the project manager Scott Schneider, at 415-258-4653, or sschneider@townofsananselmo.org

2016 Pavement Rehabilitation and Preservation Project

08/24/2016: Notice to Property Owner and/or Resident: Road Work on Arroyo Ave, August 25th & August 26th, 09:00 AM - 05:00 PM

08/03/2016: Notice to Property Owner and/or Resident: Night work on Sir Francis Drake Blvd

Bid Abstract

Addendum #1

Notice to Bidders

Plans

Specs

Bid Book (Not for Submittal) 


Project #1516: Slurry Seal Update 2 - June 27 & 28 


Project #1516C: Slurry Seal Update 1


Under Construction: FY 2014/15 Pipeline Rehabilitation Projects -- work scheduled to be completed in June 2016 

Sewer System Repair and Replacement Work in Various Areas Around San Anselmo 

-- The contractor is Maggiora & Ghilotti and the Project Owner is Ross Valley Sanitary District

-- The contractor is required to give residents 72 hour notice if the work will affect your driveway access

-- The Construction Manager for RVSD is Justin (530) 966-7901


Work has or will occur on the following streets: 

Meadowcroft, Hampton, Smith, Sais, 37 Morningside, Morningside, Calumet, Scenic, Canyon, Ivy, Sir Francis Drake, Broadmoor, Lincoln Park, El Cerrito, San Rafael, Brookside, Mountain View, Shady Lane, Saunders


Magnolia Avenue Letter to Owners & Residents

Sir Francis Drake Letter to Owners & Residents


Safe Routes to School Project

Notice to Bidder's

Addendum No.1

Federal Wage Rates 4/19/2016

Addendum No.2

Bid Results

Plans


--The start date is not yet known, but the project is expected to be complete by June 30th, 2016

--Residents will receive a notice once a contractor and a time frame are established

--Notice to Bidder's has been published, and Bid Packages are available at the Ross Valley Sanitary District office located at 2960 Kerner Boulevard, San Rafael, CA 94901


Notice to Bidder's link


PAST PROJECTS - 2016

Night work SFD: June 20,21,22


Paving Magnolia Ave. - June 24 & 25


Urgent sewer repair on Saunders resulting in street closure

Sir Francis Drake Night Work Update 8/18/15

Night Work at the Hub Work Update 7/29/15


PAST PROJECTS - 2015

2015 Pavement Rehab & Preservation Project

Notice to Bidders

Bid holder's list


2015 Sir Francis Drake Paving Project Phase 1

Sir Francis Drake Project - Notice to Bidders

The Town of San Anselmo is inviting sealed proposals for the 2015 Sir Francis Drake Pavement Project. 

Notice to Bidders 


Bids were opened June 30th, 2015. The apparent low bidder is Ghilotti Brothers. 

Bid Abstract


2015 Street Rehabilitation Project (more information)


Ghilotti Bros. will be replacing curb ramps and sidewalk at the HUB for the Town of San Anselmo on July 6th, 7th and 8th. 

Expect consistent minor traffic delays in all directions and significant delays in the northwest-bound direction during the morning commute of July 7th. 


2015 Pavement Maintenance Work


The Town is performing slurry seal on two main roads this month: 

  1. San Anselmo Avenue (between Ross Ave and Center Blvd): The work will require road closure on July 13th from 8 p.m. to 7 a.m. There will be posted traffic detours for bicycles and cars via Cedar Street
  2. Red Hill: The work will require road closure of eastbound Red Hill Avenue on July 14th, and lane closure of westbound Red Hill Ave on July 15th, from 8 p.m. to 7 a.m. There will be posted traffic detours for bicycles and cars via Greenfield Ave . The intersection at Sequoia will remain open at all times.

Pavement Maintenance on San Anselmo Ave (between Ross Ave and Center Blvd). Road Closed 8PM July 13th to 7AM July 

Lanes Closed, Follow Detours


2015 Public Works Projects 


Street Rehabilitation and Utilities projects.

Natural Gas Distribution Line Replacement


Sir Francis Drake

Sir Francis Drake update


Ridge Road 

Ridge Road update

Ridge Road Door Hanger

Ridge Road Information


Lomas Robles 

Lomas Robles Outreach

Hub Night Work information 

PG & E - Notice of Gas Line Replacement at Hub - March 16 - April 30 2015 


Thank you for your patience and considerations during periods of road sealings. Please do your best to protect the road surface while it cures. The slurry seal can be damaged by sharp turning during the curing phase. This damage can be avoided by making wide turns and always making sure the vehicle is moving before turning the steering wheel. If the road is not a dead end road please choose to drive straight through instead of performing a u-turn. "Slurry Seal Do's and Don'ts".


PAST PROJECTS - 2014


2014 Slurry Seal - Project "B"

 


The Town has contracted Ghilotti Construction with Bond Blacktop to perform the slurry seal project. Slurry sealing is an aggregate and emulsion coating applied to roads in good condition to prolong their life. The contractor is planning to preform the slurry seal on October 10th and October 14, 2014. Please note these dates and times are subject to change. The contractor will notify residents by posting a door hanger at effected properties.


The streets tentatively scheduled for this work are: Broadmoor Ave 

Brookmont Circle 

The Alameda (Holstein to 241 The Alameda)


For street slurry schedule date and time here 

To help us achieve a successful sealing here

Thank you for your patience while we coordinate the work.

The slurry seal will help protect the asphalt from ultra violet and rain infiltration which cause further cracking and deterioration. These streets have already received rubberized crack seal treatment for major cracks. Several of these streets have localized areas of pavement failure. In July, contractor crews will be removing and replacing these localized areas in preparation of the slurry seal.

2014 Slurry Seal - Project "A" (more information)

 

PAVEMENT PRESERVATION 

Our Pavement Rehabilitation project for 2014 performs asset protection in the form of preventive maintenance such as a slurry seal. It is less expensive to prolong the life of good asphalt with maintenance, then to wait until it deteriorates so far that it needs full replacement. Preventative maintenance is a cost effective way to extend the life of the pavement saving both cost and environmental impact.SLURRY SCHEDULE FOR GROUP A
SLURRY SCHEDULE FOR GROUP A - by street & date 

SLURRY SEAL NEIGHBOR NOTICE


The streets scheduled for this work are: 


GROUP A 

Center Blvd (between San Rafael and Forest) Woodland Avenue (between Cedar and San Anselmo Ave)

Ross Avenue (between Cedar and San Anselmo Ave)

Tunstead Avenue

Sequoia (between Millbrae and Hilldale)

Jones Street

Richmond (Bolinas to Mariposa)

Miwok Drive

Nokomis Avenue 

2014 Street Rehabilitation Project (more information)

The Town is designing for the 2014 Street Rehabilitation project. The project scope includes repaving the following streets: The Alameda from Arroyo to the Town Limits, Sunview Avenue, Toyon Terrace, Berkeley Avenue from Sunview to Broadmoor, and Oak Knoll Avenue.

 


Road Resurfacing Schedule

Sunview Ave Toyon Terrace

Berkeley Ave (Sunview to Broadmoor)

Oak Knoll Ave


Project documents


Bid Results 

Addendum 1 Part A 

Addendum 1 Part B 

Bid Holders List 

Notice to Bidders


Projects Pending Award Magnolia Avenue - Estimated paving date: October 1, 2014


2014 LED Street Light Retrofit Project There are 411 high pressure sodium (HPS) street lights throughout the Town of San Anselmo. The 2014 LED Street Light Retrofit project will convert these street lights to energy efficient Light Emitting Diode (LED) lights that will greatly reduce the Town’s energy consumption while at the same time maintaining existing light levels. The proposed project is in accordance with the Town’s Climate Action Change Plan and will reduce Green House Gas Emissions by approximately 140,000 lbs CO2 per year, removing the equivalent of 12 cars off the road per year. Conversion of the street lights to LED by the Town’s contractor DC Electric, Inc. will begin the week of June 30, 2014. The work is expected to take 3 weeks to complete during which time there will be construction traffic controls, lane closures and parking restrictions at various locations around Town between the hours of 8:30am and 5:00pm. Conversion of lights on Sir Francis Drake Boulevard and Red Hill Avenue maybe completed at night to avoid traffic interruptions. A map of the existing street lights to be converted is available at: https://batchgeo.com/map/97ab43506007e5d22b9818d83c956267 Please contact the Town’s Project Manager by phone at (415) 258-4654 or by email at dblomquist@townofsananselmo.org if you have any questions. 2014 Capital Improvement Project Updates

2014 Utility Projects


MMWD - Replacement of Water Main 

Greenfield Ave between Spring Grove and Sequoia 

Bridge Ave 

Sunview Ave 


RVSD - Replacement and/or repair of Sewer System

FY 2014 Gravity Sewer Rehab Project Public Notification 

Sir Francis Drake Blvd (Pastori Ave to Kent Ave) 

Monterey Terrace

East Court to Fairview Court (easement) 

Scenic Ave 

Crescent Rd 

Roger Ave 

Greenfield Ave (Greenfield Court to Terrace Ave) 


PG&E - Natural Gas Distribution Line Replacement

Oak Knoll Ave

SunviewAve

Floribel (No.40 to No.101)

Berkeley(Sunview to Broadmoor)

Berkeley Ave and Sunview Ave - PG&E Community Notice 

Oak Knoll Rd - PG&E Community Notice PG&E - Utility Pole Replacement PG&E and its contractor, PAR Electric, will be starting work in March 2014 at various locations; The work will include replacement of several utility poles and service conductors. The locations and dates of work are as follows: Location Street Date 

6 604 San Anselmo Ave 3/17/2014

5 114 Sycamore Ave 3/18/2014

8 36 Ross Ave 3/19/2014

4 118 Sycamore Ave 3/19/2014

8 36 Ross Ave 3/20/2014

1.3 126 & 13 Sycamore Ave 3/20/2014

7 12 Tamalpais Ave 3/21/2014 


PG&E - Pressure Test 

Pacific Gas and Electric Company (PG&E) is performing a hydrostatic pressure test on our natural gas pipeline. This is part of a system-wide program to ensure the safety of the transmission pipelines that deliver gas across the region. PGE will be testing at locations on westbound Red Hill Avenue, and westbound Center Street in San Anselmo (near the HUB). Work will begin at the end of May and last until mid-August, although weather and other factors affecting safe working conditions could change the schedule.

What to expect:

This test involves excavating around parts of the existing underground pipeline, filling the pipeline with water, and increasing the pressure to a level that is much higher than the pipeline’s normal operating pressure with natural gas. The test will confirm the pipeline’s safe operating pressure and reveal any potential weaknesses. If the pipe does not meet acceptable standards, it will be repaired or replaced with new pipe. During this test, you will see PG&E and contractor trucks, water tanks, and heavy equipment. Your gas service will continue without interruption in most cases. If that changes, a PG&E representative will contact you. At times, you may smell gas and hear a loud, steady noise as we vent natural gas from the pipeline using safe and common techniques. Although this is normal when crews are working, we encourage anyone who has concerns about he smell of gas to call us 24 hours a day at 1-800-743-5000. PG&E will clearly mark all work areas, and traffic flaggers will help to direct traffic. Please plan for minor delays when driving through this area. If you have any questions or concerns about this project, please call your PGE Customer Care Representative Aaron Murphy at 707-577-1062. 


FACT SHEET click here Pacific Gas and Electric Company is performing a hydrostatic pressure test on their natural gas pipeline.

Please remember as you are working in your yard, no project is too small to call 811. 


CALL 811 BEFORE YOU DIG